# Closing & Opening Milestones

## Closing Milestones

<details>

<summary>Step 1: Select a Milestone from the table view and click "Close"</summary>

In the Milestones tab of your Project click on the "Open" button and click on the kebob icon for the Milestone you wish to re-open. Next, click "Close"

</details>

<figure><img src="https://1326643208-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FnpMhTPhBTwVaw7bZVBjY%2Fuploads%2Fgit-blob-cab60844770131f78da5b02c75613c1e78927187%2F307_Milestones%2009_Milestones%20-%20More%20-%20Close.png?alt=media" alt=""><figcaption><p>Click on the kebob icon next to the Milestone you want to Close, and then click the Close button.</p></figcaption></figure>

<details>

<summary>Step 2: Confirm the Closing of a Milestone</summary>

A notification will appear asking you to confirm your choices. Click "Close milestone" to continue, otherwise click "Cancel" to go back.\
\
A confirmation toaster will appear on the bottom right of your screen telling you the Milestone has been Closed.

</details>

<div><figure><img src="https://1326643208-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FnpMhTPhBTwVaw7bZVBjY%2Fuploads%2Fgit-blob-2ca6a454c93f6139f0deb6e570a4dcc75729f3d5%2F308_Milestones%2010_Milestones%20-%20More%20-%20Close.png?alt=media" alt=""><figcaption><p>You can Close a Milestone even if all the test runs have not been completed.</p></figcaption></figure> <figure><img src="https://1326643208-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FnpMhTPhBTwVaw7bZVBjY%2Fuploads%2Fgit-blob-8305224495c3b1cd3391a2d672621310625508c0%2F305_Milestones%2007_Milestones%20-%20More%20-%20Delete.png?alt=media" alt=""><figcaption><p>A confirmation toaster will appear on the bottom right confirming your action.</p></figcaption></figure></div>

## Opening Milestones

<details>

<summary>Step 1: Select the Milestone from the table view and click "Re-open"</summary>

In the Milestones tab of your Project click on the "Closed" button and click on the kebob icon for the Milestone you wish to re-open. Next, click "Re-open"\
\
The Closed Milestone will reappear in the open Table View of Milestones.

</details>

<figure><img src="https://1326643208-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2FnpMhTPhBTwVaw7bZVBjY%2Fuploads%2Fgit-blob-37ca108c07cbc3d00008f3e57ff30896d8f26a75%2F297_Milestones%2003_Milestones%20-%20Closed%20-%20expanded%20menu.png?alt=media" alt=""><figcaption><p>Choose the Milestone you want to Open and click the Re-open button.</p></figcaption></figure>

Now that you know what Milestones are and how to change their status, we will explain how to create a new Milestone. Click "Next"